Project Description:
MIDDLEBOROUGH- INTERSECTION IMPROVEMENTS & RELATED WORK AT JOHN GLASS SQUARE
This project is intended to improve traffic flow along with multi-modal accommodation and safety at John Glass Square, which is a 6-legged intersection located in a small urban Central Business District. The approach streets are: Centre Street, Centre Avenue, Everett Street, High Street and Station Street. A second location to be addressed is the nearby intersection of Centre Street and Oak Street to the East. Each of these intersections experience considerable pedestrian traffic. The project is also intended to provide street side amenities for bicyclists and pedestrians.
Location:
  • Town of Middleborough
  • Construction Begins: Summer 2020
    Resident Engineer: Trevor O'Bryan
    Construction Bid Price: $2,920,595.50
    District: District 5

    Contracts (1) Progress
    # 111847 -- Construction Contract
    Intersection Improvements and Related Work at Jack Glass Square Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 09/10/2020
    Contract Information
    Project Designer: Municipality
    Funding Source: FA - Surface Trans. Block Grant (STBG)
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 09/27/2013
    Project Initiation Form PIF Entered 11/04/2013
    Project Initiation Form PRC Submitted 11/14/2013
    Project Review Committee PRC Approved 04/07/2014
    Project Status Advertised 07/04/2020
    Project Management
    100% Design 100% Package Received 07/22/2019
    100% Design 100% Package Comments to DE 01/24/2020
    25% Design 25% Package Received 11/02/2017
    25% Design 25% Package Comments to DE 01/25/2018
    25% Design Design Public Hearing 06/27/2018
    75% Design 75% Package Received 01/22/2019
    75% Design 75% Package Comments to DE 05/09/2019
    Final Design PS&E Received 04/15/2020
    Final Design PS&E Received - Resub 1 06/19/2020