FALL RIVER- NEW BEDFORD- BRIDGE REPLACEMENTS, F-02-091, COUNTRY CLUB ROAD OVER MAC RR, F-02-029, MAC RR OVER BROWNELL STREET, F-02-030, MAC RR OVER PRESIDENT AVENUE, & N-06-024, MAC RR OVER ROUTE 18 & WAMSUTTA STREET
Work consists of replacing F-02-091, F-02-029, F-02-030 & N-06-024 in Fall River and New Bedford.
Location:
  • City of Fall River
  • City of New Bedford
  • Resident Engineer: Rajat Gogoi
    Construction Contract Value: $49,764,334.00
    Construction Bid Price: $41,984,290.50
    Initial Construction Estimate: $52,038,077.40
    District: District 5

    Contracts (4) Progress
    # 55038 -- Design -- Bridge Rehab/Recon/New Const
    Work will consist of structural evaluations and emergency design support services to support the Bridge Preservation/Betterment Advertisement Program. Final
    # 77887 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 80651 -- Non-system contract type
    Statewide - Owner's Representative will perform peer reviews and manage cost recovery and value engineering
    # 83799 -- Construction Contract
    Replacement of 4 Bridges (Steel) Along the Future South Coast Rail Line (Br. Nos. F-02-029, F-02-030, F-02-091, N-06-024). Completed

    Bridges

    Contract Dates
    Notice to Proceed: 12/18/2014
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 10/10/2013
    Project Initiation Form PIF Entered 10/10/2013
    Project Initiation Form PRC Submitted 10/10/2013
    Project Review Committee PRC Approved 10/11/2013
    Project Status Advertised 07/26/2014
    Project Management
    100% Design 100% Package Received 04/24/2014
    25% Design 25% Package Comments to DE 02/24/2014
    75% Design 75% Package Received 04/24/2014
    Final Design PS&E Received 07/21/2014
    Final Design PS&E to FAPRO 07/24/2014