SPRINGFIELD- VIADUCT DECK REPLACEMENT OF S-24-061 ON I-91 (EARLY ACTION)
The project is the "Early Action" replacement of deteriorated deck sections of the I-91 Viaduct through Springfield. Minor associated steel superstrucutre repairs and painting is also proposed.
Location:
  • City of Springfield
  • Construction Begins: Spring 2015
    Resident Engineer: Daniel Shattuck
    Construction Contract Value: $175,837,490.00
    Construction Bid Price: $148,000,150.00
    Initial Construction Estimate: $193,099,000.00
    District: District 2

    Contracts (10) Progress
    # 54834 -- Design -- Bridge Rehab/Recon/New Const
    Work will consist of structural evaluations and emergency design support services to support the Bridge Preservation/Betterment Advertisement Program. Final
    # 68385 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassDOT on an open end basis for various statewide highway and bridge projects. Final
    # 69761 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassDOT on an open end basis for various highway and bridge projects. Final
    # 77854 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 77862 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 77878 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 77886 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 77887 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 80655 -- Non-system contract type
    Statewide - Owner's Representative will perform peer reviews and manage cost recovery and value engineering
    # 85020 -- Construction Contract
    Rehabilitation of Viaduct Br. No. S-24-061 (Steel) along Interstate 91 Completed

    Bridges

    Contract Dates
    Notice to Proceed: 05/21/2015
    Contract Information
    Project Designer: Consultant
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 10/11/2013
    Project Initiation Form PIF Entered 10/11/2013
    Project Initiation Form PRC Submitted 10/11/2013
    Project Review Committee PRC Approved 10/11/2013
    Project Status Advertised 09/20/2014
    Project Management
    100% Design 100% Package Received 07/02/2014
    100% Design 100% Package Comments to DE 07/22/2014
    100% Design 100% Plans Approved 08/21/2014
    25% Design 25% Package Received 04/08/2014
    Final Design PS&E Received 01/07/2015
    Final Design PS&E to FAPRO 08/22/2014
    Final Design PS&E to FAPRO 02/25/2015