Project Description:
FRAMINGHAM- NATICK- COCHITUATE RAIL TRAIL CONSTRUCTION INCLUDING PEDESTRIAN BRIDGE, N-03-014, OVER ROUTE 9 & F-07-033=N-03-029 OVER ROUTE 30
The project involves construction of 2.4 miles of rail trail and includes a grade separated crossing at Route 30, as well as rehabilitation of the CSX bridge over Route 9. A section of the trail also includes a spur line connecting to the Natick Mall at Speen Street. The Trail will be, for the most part, off road with 4 at- grade roadway and 2 driveway crossings. At the northerly end, a grade separated crossing of Route 30 will constructed to provide the connection to the Framingham section of the CRT. At its southerly end, the CRT will connect to North Main Street (Route 27) on a retained fill section approximately opposite the North Street intersection.
Location:
  • Town of Framingham
  • Town of Natick
  • Construction Begins: Winter 2018/2019
    Resident Engineer: Scott Kallin
    Construction Bid Price: $9,686,436.42
    District: District 3

    Contracts (2) Progress
    # 105830 -- Construction Contract
    Construction of a Shared Use Path (Cochituate Rail Trail) Including Signals and Br. Nos. N-03-014 & F-07-033=N-03-029 over Routes 9 and 30 (Worcester Street and Commonwealth R Completed
    # 77847 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    Contract Dates
    Notice to Proceed: 03/08/2019
    Contract Information
    Project Designer: Municipality
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 10/22/2013
    Project Initiation Form PIF Entered 10/22/2013
    Project Initiation Form PRC Submitted 11/15/2013
    Project Review Committee PRC Approved 04/07/2014
    Project Status Advertised 09/08/2018
    Project Management
    100% Design 100% Package Received 04/13/2018
    100% Design 100% Package Comments to DE 05/31/2018
    25% Design 25% Package Received 10/07/2014
    25% Design 25% Package Received 07/31/2015
    25% Design 25% Package Comments to DE 11/23/2015
    25% Design 25% Package Received - Resub 2 05/10/2016
    25% Design 25% Package Received - Resub 3 01/03/2017
    25% Design Design Public Hearing 01/11/2017
    75% Design 75% Package Received 11/27/2017
    75% Design 75% Package Comments to DE 01/12/2018
    Final Design PS&E Received 06/19/2018
    Final Design PS&E to Peer Reviewer 05/18/2018
    Final Design PS&E Received - Resub 2 07/24/2018
    Final Design PS&E Received - Resub 3 08/01/2018