AUBURN- REHABILITATION OF AUBURN STREET, FROM WALSH AVENUE TO MILLBURY STREET
The project involves rehabilitation of 0.49 miles of Auburn Street, from Walsh Avenue to Millbury Street. The work includes upgrades to two signals, reconstruction of sidewalks and related work.
Location:
  • Town of Auburn
  • Construction Begins: Autumn 2020
    Resident Engineer: Jamal Bonyani
    Construction Bid Price: $3,867,688.91
    District: District 3

    Contracts (1) Progress
    # 112231 -- Construction Contract
    Roadway Reconstruction and Related Work (Including Painting and Signals) Br. No. A-17-005 along a Section of Auburn Street Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 10/05/2020
    Contract Information
    Project Designer: Municipality
    Funding Source: Highway Safety Improvement Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 10/22/2013
    Project Initiation Form PIF Entered 10/22/2013
    Project Initiation Form PRC Submitted 11/15/2013
    Project Review Committee PRC Approved 04/07/2014
    Project Status Advertised 07/25/2020
    Project Management
    100% Design 100% Package Received 04/13/2020
    100% Design 100% Package Comments to DE 05/22/2020
    25% Design 25% Package Received 04/03/2018
    25% Design 25% Package Comments to DE 09/13/2018
    25% Design Design Public Hearing 06/27/2019
    75% Design 75% Package Received 11/07/2019
    75% Design 75% Package Comments to DE 01/21/2020
    Final Design PS&E Received 06/25/2020
    Final Design PS&E to FAPRO 07/14/2020