Project Description:
CHICOPEE- SOUTH HADLEY- SIGNAL & INTERSECTION IMPROVEMENTS AT 13 INTERSECTIONS ALONG ROUTE 33 (MEMORIAL DRIVE), FROM FULLER ROAD TO ABBEY STREET
This project is a safety improvement project that will upgrade the existing signal equipment at several high crash locations along route 33 and will improve traffic signal timing and phasing and allow for better traffic flow. Other improvements will include new pavement markings, signage and improved pedestrian access. Intersections include Route 33 at Fuller Road, Shop Rite Shopping Center, Mass Turnpike, Chicopee Marketplace North Drive, Westover Rd/Granby Rd, Pendleton Avenue, Irene St/Jamrog Dr, Streiber Drive, Fairview Shopping Ctr, James Street, Britton Street, New Ludlow Street and Abbey Street.
Location:
  • City of Chicopee
  • Town of South Hadley
  • Construction Begins: Winter 2019/2020
    Resident Engineer: Andrew Grden
    Construction Bid Price: $5,356,250.00
    District: District 2

    Contracts (2) Progress
    # 109468 -- Construction Contract
    Signal and Intersection Improvements at 13 Locations along Route 33 (Memorial Drive) Completed
    # 77887 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 01/31/2020
    Contract Information
    Project Designer: Consultant
    Funding Source: Highway Safety Improvement Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 10/24/2013
    Project Initiation Form PIF Entered 10/24/2013
    Project Initiation Form PRC Submitted 10/24/2013
    Project Review Committee PRC Approved 11/20/2013
    Project Status Advertised 08/24/2019
    Project Management
    100% Design 100% Package Received 02/08/2019
    100% Design 100% Package Comments to DE 03/15/2019
    25% Design 25% Package Received 04/07/2017
    25% Design 25% Package Comments to DE 09/14/2017
    25% Design Design Public Hearing 05/24/2018
    75% Design 75% Package Received 09/28/2018
    75% Design 75% Package Comments to DE 11/16/2018
    Final Design PS&E Received 07/16/2019
    Final Design PS&E Received - Resub 1 08/09/2019