Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
AMESBURY- SALISBURY- TRAIL CONNECTOR @ I-95
The proposed trail would follow the railroad bed west from Rabbit Road for 1,300 feet and would pass under three I-95 bridges. The second section between the railroad bed and Old Elm Street includes 800 feet of trail on MassDOT property abutting the I-95 SB on-ramp. The third trail section is Old Elm Street in Amesbury which is a dead end roadway and a trail head will be developed. The project would also include a widened sidewalk along the west side of Rabbit Road to make a section of shared use path from the trail crossing to Route 110. The final part is the stairs from the Whittier Bridge Shared Use Path to Main Street/Evans Place and the Amesbury Visitors Center.
Location:
  • Town of Amesbury
  • Town of Salisbury
  • Construction Begins: Spring 2019
    Resident Engineer: Jeffrey Lavallee
    Construction Bid Price: $3,248,692.00
    District: District 4

    Contracts (3) Progress
    # 105914 -- Construction Contract
    Construction of two Shared Use Paths (Ghost and Garrison Trail Extension) Including Signals and Br. No. A-07-017 under Interstate 95 Completed
    # 77878 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 86785 -- Design -- Services
    Work will consist of performing the collection of electronic field survey data and the completion of AutoCAD Base Plans for highway and bridge projects throughout District 4. Final

    Bridges

    Contract Dates
    Notice to Proceed: 04/18/2019
    Contract Information
    Project Designer:
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 10/25/2013
    Project Initiation Form PIF Entered 10/28/2013
    Project Initiation Form PRC Submitted 11/05/2013
    Project Review Committee PRC Approved 04/07/2014
    Project Status Advertised 09/15/2018
    Project Management
    100% Design 100% Package Received 06/12/2018
    25% Design 25% Package Received 09/17/2015
    25% Design 25% Package Comments to DE 06/15/2016
    25% Design Design Public Hearing 05/09/2017
    75% Design 75% Package Received 02/05/2018
    Final Design PS&E Received 08/10/2018
    Final Design PS&E to FAPRO 08/24/2018