Project Description:
BEDFORD- MINUTEMAN BIKEWAY EXTENSION, FROM LOOMIS STREET TO CONCORD ROAD (ROUTE 62)
The Minuteman Bikeway currently ends at Depot Park, in Bedford, near the intersection of South Road and Loomis Street. This project proposes to extend the bikeway by making a 1,665 foot portion of Railroad Avenue accessible to bikes, and constructing 8,800 feet of bikeway on the Reformatory Branch Trail, from Railroad Avenue past Concord Road to Wheeler Drive, near the Bedford/Concord Town line. As a part of the Railroad Avenue reconstruction, sidewalks, bike accommodations, new drainage, pavement markings and signs and defined curb cuts will be constructed.
Location:
  • Town of Bedford
  • Design Responsibility: Municipality
    Right of Way Responsibility: Municipality
    Construction Begins: Autumn 2022
    Project Manager: Greg Frazier
    Estimated Total Contract Cost: $10,459,693.05
    Estimated Total Federal Participating Construction Cost: $10,996,288.20
    Funding Provision: This project is planned to be funded through the 2022 Transportation Improvement Program for the Boston Metropolitan Planning Organization.
    District: District 4
    Current Status: 75% Package Comments to DE (as of 02/08/2021 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2022
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: BEDFORD
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • TAP revised from $841,076 to $1,500,000 via STIP Action 6. project moved to 2022.
  • Category FA - Trans. Alternative Prgm (TAP)
    Federal Cost: $1,200,000.00
    State Cost: $300,000.00
    Total Cost: $1,500,000.00

    Planned Federal FY: 2022
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: BEDFORD
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • CMAQ revised from $6,489,964 to $9,500,168 via STIP Action 6. Project moved to 2022.
  • Category FA - Congestion Mitigation/Air Quality (CMAQ)
    Federal Cost: $7,600,134.40
    State Cost: $1,900,033.60
    Total Cost: $9,500,168.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 10/30/2013
    Project Initiation Form PIF Entered 10/30/2013
    Project Initiation Form PRC Submitted 11/05/2013
    Project Review Committee PRC Approved 04/07/2014
    Project Management
    25% Design 25% Package Received 04/18/2017
    25% Design 25% Package Received 03/03/2020
    25% Design Design Public Hearing 02/06/2020
    75% Design 75% Package Received 11/03/2020
    75% Design 75% Package Comments to DE 02/08/2021