Project Description:
ACTON- INTERSECTION & SIGNAL IMPROVEMENTS ON SR 2 & SR 111 (MASSACHUSETTS AVENUE) AT PIPER ROAD & TAYLOR ROAD
Work consists of intersection Safety upgrades for signs, pavement markings, and traffic signals as identified through a Road Safety Audit Process in the town Acton.
Location:
  • Town of Acton
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Spring 2029
    Project Manager: Lawrence Cash
    Estimated Total Contract Cost: $9,104,748.00
    Estimated Total Federal Participating Construction Cost: $9,712,100.00
    Funding Provision: This project is planned to be funded through the 2029 Transportation Improvement Program for the Boston Metropolitan Planning Organization.
    District: District 3
    Current Status: 25% Package Comments to DE (as of 06/20/2019 )

    Contracts (1) Progress
    # 77884 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2029
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: ACTON
    Category: Advertised Projects Constr.
    Budget Section: 2B
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Hwy Safety Improvement Prgm (HSIP)
    Federal Cost: $10,139,432.40
    State Cost: $1,126,603.60
    Total Cost: $11,266,036.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 10/31/2013
    Project Initiation Form PIF Entered 10/31/2013
    Project Initiation Form PRC Submitted 10/31/2013
    Project Review Committee PRC Approved 11/05/2013
    Project Management
    25% Design 25% Package Received 03/11/2019
    25% Design 25% Package Comments to DE 06/20/2019