Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
MILTON- INTERSECTION & SIGNAL IMPROVEMENTS AT GRANITE AVENUE & SQUANTUM STREET
Work consists of intersection safety upgrades for signs, pavement markings, and traffic signals as identified through a Road Safety Audit Process.
Location:
  • Town of Milton
  • Construction Begins: Spring 2018
    Resident Engineer: Fritz Dubuisson
    Construction Bid Price: $682,900.00
    District: District 6

    Contracts (2) Progress
    # 102283 -- Construction Contract
    Intersection Improvements and Related Work (Including Signals) Granite Avenue at Squantum Street. Completed
    # 77876 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 04/24/2018
    Contract Information
    Project Designer: Consultant
    Funding Source: Highway Safety Improvement Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 10/31/2013
    Project Initiation Form PIF Entered 10/31/2013
    Project Initiation Form PRC Submitted 10/31/2013
    Project Review Committee PRC Approved 11/05/2013
    Project Status Advertised 09/16/2017
    Project Management
    100% Design 100% Package Received 07/24/2017
    100% Design 100% Package Comments to DE 08/21/2017
    25% Design 25% Package Received 06/22/2016
    25% Design 25% Package Comments to DE 11/01/2016
    25% Design 25% Package Received - Resub 1 12/09/2016
    25% Design Design Public Hearing 03/29/2017
    Final Design PS&E Received 09/01/2017
    Final Design PS&E to Peer Reviewer 09/12/2017
    Final Design Peer Review Comments to DE 10/05/2017
    Final Design PS&E to FAPRO 09/05/2017
    Final Design PS&E Received - Resub 1 11/06/2017