Project Description:
WEYMOUTH- INTERSECTION & SIGNAL IMPROVEMENTS AT 2 LOCATIONS: SR 53 (WASHINGTON STREET) AT MUTTON LANE & PLEASANT STREET
Work consists of intersection safety upgrades for signs, pavement markings, and traffic signals as identified through a Road Safety Audit Process.
Location:
  • Town of Weymouth
  • Construction Begins: Winter 2016/2017
    Resident Engineer: Roderick Connelly III
    Construction Bid Price: $1,101,707.00
    District: District 6

    Contracts (2) Progress
    # 77876 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 96618 -- Construction Contract
    Intersection Improvements at 2 Locations along a Section of Route 53 (Washington Street). Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 01/25/2017
    Contract Information
    Project Designer: Consultant
    Funding Source: Highway Safety Improvement Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 10/31/2013
    Project Initiation Form PIF Entered 10/31/2013
    Project Initiation Form PRC Submitted 10/31/2013
    Project Review Committee PRC Approved 11/05/2013
    Project Status Advertised 07/30/2016
    Project Management
    100% Design 100% Package Received 05/09/2016
    100% Design 100% Package Comments to DE 06/14/2016
    100% Design 100% Plans Approved 06/14/2016
    100% Design 100% Plans Complete 06/14/2016
    25% Design 25% Package Received 01/15/2016
    25% Design 25% Package Comments to DE 03/10/2016
    25% Design 25% Package Approved 03/11/2016
    25% Design Design Public Hearing 06/23/2016
    25% Design 25% Plans Complete 04/28/2016
    75% Design 75% Package Received 05/09/2016
    75% Design 75% Package Comments to DE 06/14/2016
    75% Design 75% Plans Approved 06/14/2016
    75% Design 75% Plans Complete 06/14/2016
    Final Design PS&E Received 07/08/2016
    Final Design PS&E to Peer Reviewer 05/16/2016
    Final Design Peer Review Comments to DE 06/06/2016
    Final Design PS&E to FAPRO 07/22/2016
    Consultant Contract Process Scope to DE 05/21/2015
    Consultant Contract Process NTP Issued 08/12/2015
    Consultant Contract Process Workhours Approved 07/09/2015