SWAMPSCOTT- INTERSECTION & SIGNAL IMPROVEMENTS AT SR 1A (PARADISE ROAD) AT SWAMPSCOTT MALL
Work consists of intersection safety upgrades for signs, pavement markings, and traffic signals as identified through a Road Safety Audit Process.
Location:
  • Town of Swampscott
  • Construction Begins: Spring 2021
    Resident Engineer: Carmen Ilardi
    Construction Bid Price: $1,271,352.03
    District: District 4

    Contracts (4) Progress
    # 114156 -- Construction Contract
    Intersection Improvements and Related Work (Including Signals) Route 1A (Paradise Road) at Swampscott Mall Road Completed
    # 115791 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final
    # 77859 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 77864 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 05/25/2021
    Contract Information
    Project Designer: Consultant
    Funding Source: Highway Safety Improvement Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 11/01/2013
    Project Initiation Form PIF Entered 11/01/2013
    Project Initiation Form PRC Submitted 11/01/2013
    Project Review Committee PRC Approved 11/05/2013
    Project Status Advertised 03/13/2021
    Project Management
    100% Design 100% Package Received 02/24/2020
    100% Design 100% Package Comments to DE 03/25/2020
    100% Design 100% Plans Complete 03/25/2020
    25% Design 25% Package Received 02/28/2018
    25% Design 25% Package Received 02/28/2018
    25% Design 25% Package Received 02/24/2020
    25% Design 25% Package Received - Resub 1 02/11/2019
    25% Design Design Public Hearing 08/08/2019
    75% Design 75% Package Received 02/24/2020
    75% Design 75% Package Comments to DE 03/25/2020
    75% Design 75% Plans Complete 03/25/2020
    Final Design PS&E Received 10/21/2020
    Final Design PS&E to FAPRO 03/01/2021