Project Description: |
SHREWSBURY- INTERSECTION & SIGNAL IMPROVEMENT AT US 20 (HARTFORD TURNPIKE) AT GRAFTON STREET
Work consists of intersection safety upgrades for signs, pavement markings, and traffic signals as identified through a Road Safety Audit Process.
|
Location: |
|
Design Responsibility: | Consultant |
Right of Way Responsibility: | MassDOT |
Construction Begins: | Spring 2028 |
Project Manager: | Muazzez G Reardon![]() |
Estimated Total Contract Cost: | $14,378,625.00 |
Estimated Total Federal Participating Construction Cost: | $15,218,850.00 |
Funding Provision: | This project is planned to be funded through the 2028 Transportation Improvement Program for the Central Massachusetts Metropolitan Planning Organization. |
District: | District 3 |
Current Status: | 25% Package Received - Resub 1 (as of 02/12/2025 ) |
|
Bridges |
|
|
|