Project Description:
SHREWSBURY- ROADWAY RECONSTRUCTION ON ROUTE 20, FROM PURINTON STREET TO THE ROUTE 140 ON-RAMP
The proposed project includes reconstruction of the existing signal, including widening for protected turn lanes. Additional work includes construction of a section of sidewalk and shared use path, retaining walls, minor drainage modifications, utility relocations and related work such as improved signage and pavement markings. The limits for work extend from Purinton Street to the Route 140 on-ramp.
Location:
  • Town of Shrewsbury
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Spring 2030
    Project Manager: Muazzez G Reardon
    Estimated Total Contract Cost: $14,330,700.00
    Estimated Total Federal Participating Construction Cost: $15,169,150.00
    Funding Provision: This project is planned to be funded through the 2028 Transportation Improvement Program for the Central Massachusetts Metropolitan Planning Organization.
    District: District 3
    Current Status: 25% Package Received - Resub 1 (as of 02/12/2025 )

    Contracts (2) Progress
    # 77875 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 86790 -- Design -- Services
    AutoCAD Base Plan Surveying Services Final

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2028
    Responsible MPO: Central Massachusetts Metropolitan Planning Organization
    Location: Municipality
    Cities: SHREWSBURY
    Category: Advertised Projects Constr.
    Budget Section: 2B
    Advance Construct: No
    Air Quality Exempt: No

  • Construction, Total Project Cost = $10,486,334, Design Status = 25%, YOE = 12%
  • Category FA - Hwy Safety Improvement Prgm (HSIP)
    Federal Cost: $9,437,700.60
    State Cost: $1,048,633.40
    Total Cost: $10,486,334.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 11/01/2013
    Project Initiation Form PIF Entered 11/01/2013
    Project Initiation Form PRC Submitted 11/01/2013
    Project Review Committee Received 05/28/2025
    Project Review Committee PRC Approved 11/05/2013
    Project Management
    25% Design 25% Package Received 03/02/2018
    25% Design 25% Package Comments to DE 08/08/2018
    25% Design 25% Package Received - Resub 1 02/12/2025
    Consultant Contract Process NTP Issued 09/03/2014