Project Description: |
SHREWSBURY- INTERSECTION & SIGNAL IMPROVEMENT AT US 20 (HARTFORD TURNPIKE) AT GRAFTON STREET
Work consists of intersection safety upgrades for signs, pavement markings, and traffic signals as identified through a Road Safety Audit Process.
|
Location: |
|
Design Responsibility: | Consultant |
Right of Way Responsibility: | MassDOT |
Construction Begins: | Spring 2028 |
Project Manager: | Muazzez G Reardon |
Estimated Total Contract Cost: | $8,658,354.73 |
Estimated Total Federal Participating Construction Cost: | $9,362,797.78 |
Funding Provision: | This project is planned to be funded through the 2028 Transportation Improvement Program for the Central Massachusetts Metropolitan Planning Organization. |
District: | District 3 |
Current Status: | 25% Package Comments to DE (as of 08/08/2018 ) |
|
Bridges |
|
|
|