Project Description:
DISTRICT 5- EMERGENCY & NON-ROUTINE STEEL BEAM REPAIRS AT VARIOUS LOCATIONS
This contract will be used to correct structural deficiencies on the ends of steel beams which require immediate repair.
Location:
Resident Engineer: Alex Lustikman
Construction Contract Value: $1,503,885.26
Construction Bid Price: $1,298,900.00
Initial Construction Estimate: $1,242,150.00
District: District 5

Contracts (1) Progress
# 82509 -- Construction Contract
Scheduled and Emergency Bridge Structural Steel Beam End Repairs (Including Painting) at Various Locations. Completed

Bridges

Contract Dates
Notice to Proceed: 10/29/2014
Contract Information
Project Designer: In-House Boston
Funding Source: Non Federal Aid
See the Milestone Details tab for additional Project information
Property Impacts - Right of Way
no comments
Environmental Impacts
no comments
Project Design
no comments
Project Funding
no comments
Public Involvement
no comments
Construction
no comments
Accelerated Bridge Program
no comments
No TIP Data Available For This Project
Project Task Information
Project Status
Project Need Form PNF Entered 11/05/2013
Project Initiation Form PIF Entered 11/05/2013
Project Initiation Form PRC Submitted 11/05/2013
Project Review Committee PRC Approved 03/18/2014
Project Status Advertised 05/24/2014
Project Management
100% Design 100% Package Received 03/14/2014
Final Design PS&E Received 05/12/2014
Final Design PS&E to FAPRO 05/13/2014