Project Description:
WESTFIELD- IMPROVEMENTS & RELATED WORK ON ROUTE 20, COURT STEET & WESTERN AVENUE, LLOYDS HILL ROAD TO HIGH STREET/MILL STREET INTERSECTION (PHASE II)
Project includes reclamation, box-widening and resurfacing along Western Avenue and Court Street from Lloyds Hill Road to the Court St./High St./Mill St. intersection. Sidewalks, crosswalks and left turn lanes will be included.
Location:
  • City of Westfield
  • Construction Begins: Spring 2021
    Resident Engineer: Madison Bates
    Construction Bid Price: $7,923,249.61
    District: District 2

    Contracts (1) Progress
    # 114198 -- Construction Contract
    Roadway Reconstruction and Related Work (Including Signals) along Sections of Western Avenue, Lloyds Hill Road, Court, High, Mill, and West Silver Streets (Phase 2) Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 06/08/2021
    Contract Information
    Project Designer: Municipality
    Funding Source: TAP
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 11/14/2013
    Project Initiation Form PIF Entered 11/14/2013
    Project Initiation Form PRC Submitted 11/15/2013
    Project Review Committee PRC Approved 12/06/2013
    Project Status Advertised 03/20/2021
    Project Management
    100% Design 100% Package Received 08/24/2020
    100% Design 100% Package Comments to DE 10/26/2020
    25% Design 25% Package Received 11/04/2014
    25% Design 25% Package Received - Resub 1 12/04/2018
    25% Design Design Public Hearing 09/12/2019
    75% Design 75% Package Received 02/03/2020
    75% Design 75% Package Comments to DE 04/09/2020
    Final Design PS&E Received 01/26/2021
    Final Design PS&E Received - Resub 1 03/09/2021