Project Description:
NORTH ANDOVER- SAFE ROUTES TO SCHOOL (NORTH ANDOVER MIDDLE SCHOOL)
The project includes the construction of a sidewalk along the southerly side of Parker Street between Greene Street and the North Andover Middle School parking lot and along the southerly side of Greene Street between Massachusetts Avenue and Faulkner Road. The intersection of Greene Street and Parker Street will be reconstructed to provide better alignment and shorter pedestrian crossings. The Greene Street easterly approach to Massachusetts Avenue will be reconstructed to create a standard T-type intersection. The Greene Street westerly approach to Massachusetts Avenue will be reconstructed to provide better alignment with Mifflin Drive and a reduction in pavement width. The construction of a crosswalk on Massachusetts Avenue just south of Greene Street will allow pedestrians to access the North Andover Middle School and Atkinson Elementary Schools. These improvements will include installation of ADA-compliant wheelchair ramps and installation of MUTCD-compliant signs and pavement markings.
Location:
  • Town of North Andover
  • Resident Engineer: Mark Spinale
    Construction Bid Price: $1,161,074.62
    District: District 4

    Contracts (3) Progress
    # 64315 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 85766 -- Design -- Highway
    Work will consist of providing school assessments and preliminary and final engineering design and construction phase services to the Highway Engineering Division for the 2014 Final
    # 90468 -- Construction Contract
    Sidewalk Reconstruction and Related Work on Sections of Massachusetts Avenue, Greene, Parker and adjacent Streets (Safe Routes to School – North Andover Middle School) Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 03/04/2016
    Contract Information
    Project Designer: Consultant
    Funding Source: TAP
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 11/18/2013
    Project Initiation Form PIF Entered 11/18/2013
    Project Initiation Form PRC Submitted 12/06/2013
    Project Review Committee PRC Approved 04/07/2014
    Project Status Advertised 09/05/2015
    Project Management
    100% Design 100% Package Received 03/30/2015
    100% Design 100% Package Comments to DE 06/03/2015
    25% Design 25% Package Received 07/01/2014
    75% Design 75% Package Received 07/01/2014
    Final Design PS&E Received 08/05/2015
    Final Design PS&E to FAPRO 09/02/2015