Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
WATERTOWN- REHABILITATION OF MOUNT AUBURN STREET (ROUTE 16)
Projects involves the recontruction of Mount Auburn Street from the Cambridge City Line to the intersection with Summer Street, just east of Watertown Square, approximately 9,300 feet. The project involves revising the roadway geometry including roadway diet reduction of available number of lanes. Safety improvements, multi-modal accomodations including shared or exclusive bike lanes. Improvements to the exising traffic signal equipment and improved ADA amenities at intersections.
Location:
  • Town of Watertown
  • Construction Begins: Winter 2023/2024
    Resident Engineer: Long Le
    Construction Bid Price: $26,661,000.00
    Funding Provision: This project is planned to be funded through the 2024 Transportation Improvement Program for the Boston Metropolitan Planning Organization.
    District: District 6

    Contracts (4) Progress
    # 115797 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final
    # 124025 -- Construction Contract
    Rehabilitation of Mount Auburn Street (Route 16)
    # 77867 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 77889 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 02/27/2024
    Contract Information
    Project Designer: Municipality
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2024
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: WATERTOWN
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • TFPC: $27,899,345 (CMAQ, HSIP, STBG); 2-year AC schedule (2023-2024); MPO Evaluation Score = 75
  • Category FA - Congestion Mitigation/Air Quality (CMAQ)
    Federal Cost: $800,000.00
    State Cost: $200,000.00
    Total Cost: $1,000,000.00

    Planned Federal FY: 2024
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: WATERTOWN
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • TFPC: $27,899,345 (CMAQ, HSIP, STBG); 2-year AC schedule (2023-2024); MPO Evaluation Score = 75
  • Category FA - Surface Trans. Block Grant (STBG)
    Federal Cost: $1,995,399.20
    State Cost: $498,849.80
    Total Cost: $2,494,249.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 11/21/2013
    Project Initiation Form PIF Entered 11/21/2013
    Project Initiation Form PRC Submitted 11/21/2013
    Project Review Committee PRC Approved 04/07/2014
    Project Status Advertised 09/09/2023
    Project Management
    100% Design 100% Package Received 05/30/2023
    25% Design 25% Package Received 12/30/2019
    25% Design Design Public Hearing 11/04/2021
    75% Design 75% Package Received 10/18/2022
    Final Design PS&E Received 08/14/2023
    Final Design PS&E to FAPRO 08/28/2023