Project Description:
NORTON- MANSFIELD- RAIL TRAIL EXTENSION (WORLD WAR II VETERANS TRAIL)
This proposal is intended to extend the existing rail trail from Cobb Street, Mansfield Southerly to Hill Street and Crane Street at the Myles Standish Industrial Park in Taunton.
Location:
  • Town of Mansfield
  • Town of Norton
  • Design Responsibility: Municipality
    Right of Way Responsibility: Municipality
    Construction Begins: Winter 2022/2023
    Project Manager: Muazzez G Reardon
    Estimated Total Contract Cost: $4,630,472.04
    Estimated Total Federal Participating Construction Cost: $5,023,722.77
    Funding Provision: This project is planned to be funded through the 2022 Transportation Improvement Program for the Southeastern Massachusetts Metropolitan Planning Organization.
    District: District 5
    Current Status: 75% Package Received (as of 04/22/2021 )

    Contracts (1) Progress
    # 77847 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2022
    Responsible MPO: Southeastern Massachusetts Metropolitan Planning Organization
    Location: Municipality
    Cities: MANSFIELD
    NORTON
    Category: Advertised Projects Constr.
    Budget Section: 2C
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Congestion Mitigation/Air Quality (CMAQ)
    Federal Cost: $3,061,040.80
    State Cost: $765,260.20
    Total Cost: $3,826,301.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 12/30/2013
    Project Initiation Form PIF Entered 03/03/2014
    Project Initiation Form PRC Submitted 03/04/2014
    Project Review Committee PRC Approved 04/07/2014
    Project Management
    25% Design 25% Package Received 02/07/2018
    25% Design 25% Package Comments to DE 07/06/2018
    25% Design Design Public Hearing 08/15/2019
    75% Design 75% Package Received 04/22/2021