Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
DISTRICT 5- VEGETATION MANAGEMENT AT VARIOUS LOCATIONS
Selective application of herbicides to control overgrowth and invasives along various sections of state highway.
Location:
Resident Engineer: Joseph Auger
Construction Contract Value: $145,025.00
Construction Bid Price: $125,025.00
Initial Construction Estimate: $205,400.00
District: District 5

Contracts (1) Progress
# 82706 -- Construction Contract
Vegetation Management at Various Locations Completed

Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 12/04/2014
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 01/15/2014
    Project Initiation Form PIF Entered 01/22/2014
    Project Initiation Form PRC Submitted 03/20/2014
    Project Review Committee PRC Approved 03/25/2014
    Project Status Advertised 06/07/2014
    Project Management
    Final Design PS&E Received 03/27/2014
    Final Design PS&E to FAPRO 04/25/2014