MEDFORD- CLIPPERSHIP DRIVE PARK CONSTRUCTION
The improvements proposed are located on the grounds of the Medford Senior Center at the intersection of Clippership Drive and Riverside Avenue in Medford Square. The project involves extension of the Clippership Linear Park and Bikeway to culminate on a Peace Garden. The project includes a central seating area with water feature, seat wall, fencing, lighting, plantings, bike racks, walkways and pedestrian and bicycle connections to the adjacent uses, Clippership Park and public spaces. The proposed improvements will extend pedestrian and bicycle mobility improvements begun in Phase I and II of the project. These projects represent a segment of the Mystic River Corridor Trail system which will link recreation areas, neighborhoods and commercial nodes along the Mystic River.
Location:
  • City of Medford
  • Resident Engineer: Michael Winnick
    Construction Bid Price: $1,268,546.50
    District: District 4

    Contracts (2) Progress
    # 64315 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 88201 -- Construction Contract
    Park Construction (Including Memorial and Peace Garden) at the Corner of Clippership and Riverside Drives. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 09/03/2015
    Contract Information
    Project Designer: Municipality
    Funding Source: SECTION 125
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 01/17/2014
    Project Initiation Form PIF Received 01/27/2014
    Project Initiation Form PIF Entered 01/27/2014
    Project Initiation Form PRC Submitted 02/07/2014
    Project Review Committee PRC Approved 04/07/2014
    Project Status Advertised 05/23/2015
    Project Management
    100% Design 100% Package Received 01/28/2015
    100% Design 100% Package Comments to DE 03/16/2015
    25% Design 25% Package Received 07/25/2014
    25% Design Design Public Hearing 12/10/2014
    75% Design 75% Package Received 07/25/2014
    75% Design 75% Package Comments to DE 10/15/2014
    Final Design PS&E Received 04/14/2015
    Final Design PS&E to FAPRO 05/19/2015