Project Description:
WHITMAN- TRAFFIC SIGNAL IMPROVEMENTS & RELATED WORK ON BEDFORD STREET (ROUTE 18) AT 2 LOCATIONS: AUBURN STREET (ROUTE 14) & TEMPLE STREET (ROUTE 27)
This project is intended to address safety issues, particularly high crash rates, due to the lack of protected left turn phasing on the EB and WB approaches to Route 18. Geometric improvements are required at each intersection. In addition, there is a need to upgrade crosswalks, replace worn signage and add new pavement markings.
Location:
  • Town of Whitman
  • Construction Begins: Winter 2018/2019
    Resident Engineer: Christopher Sera
    Construction Bid Price: $4,987,401.18
    District: District 5

    Contracts (2) Progress
    # 105653 -- Construction Contract
    Intersection Improvements and Related Work (Including Signals) Bedford Street (Route 18) at Auburn and Temple Streets (Routes 14 and 27) Completed
    # 77847 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 02/22/2019
    Contract Information
    Project Designer: Consultant
    Funding Source: CONGESTION MIT. AIR QUAL.
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 01/31/2014
    Project Initiation Form PIF Entered 02/19/2014
    Project Initiation Form PRC Submitted 02/19/2014
    Project Review Committee PRC Approved 04/07/2014
    Project Status Advertised 08/25/2018
    Project Management
    100% Design 100% Package Received 07/11/2017
    100% Design 100% Package Comments to DE 09/12/2017
    25% Design 25% Package Received 11/09/2015
    25% Design 25% Package Comments to DE 02/01/2016
    25% Design 25% Package Received - Resub 1 07/07/2016
    25% Design Design Public Hearing 08/16/2016
    75% Design 75% Package Received 01/19/2017
    75% Design 75% Package Comments to DE 03/31/2017
    Final Design PS&E Received 12/21/2017
    Final Design PS&E to Peer Reviewer 09/28/2017
    Final Design Peer Review Comments to DE 10/05/2017
    Final Design PS&E Received - Resub 1 03/12/2018
    Final Design PS&E Received - Resub 2 07/16/2018