WILBRAHAM- RECONSTRUCTION OF BOSTON ROAD (ROUTE 20), FROM DUDLEY STREET TO 400 FT. EAST OF DUMAINE STREET (0.28 MILES)
Route 20 will be reconstructed from Dudley Street to Dumaine Street for a total of 0.28 miles. The project will consist of pavement milling and resurfacing and full depth reconstruction of the pavement at widening areas. Other work to be completed in this project includes new sidewalks, wheelchair ramps, driveways, drainage improvements, new light pole bases, conduit granite curbing, landscape trees and pavement markings.
Location:
  • Town of Wilbraham
  • Construction Begins: Winter 2016/2017
    Resident Engineer: Todd Moylan
    Construction Bid Price: $1,021,783.25
    District: District 2

    Contracts (2) Progress
    # 77887 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 97684 -- Construction Contract
    Roadway Reconstruction and Related Work along a Section of Route 20 (Boston Road). Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 02/08/2017
    Contract Information
    Project Designer: Consultant
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/19/2014
    Project Initiation Form PIF Entered 02/19/2014
    Project Initiation Form PRC Submitted 02/19/2014
    Project Review Committee PRC Approved 03/31/2014
    Project Status Advertised 09/03/2016
    Project Management
    100% Design 100% Package Received 10/31/2014
    100% Design 100% Package Received 06/10/2015
    100% Design 100% Package Comments to DE 01/13/2015
    100% Design 100% Package Comments to DE 07/08/2015
    25% Design 25% Package Received 07/29/2010
    25% Design Design Public Hearing 08/11/2015
    Final Design PS&E Received 02/16/2016
    Final Design PS&E to Peer Reviewer 02/18/2016
    Final Design Peer Review Comments to DE 03/14/2016
    Final Design PS&E Received - Resub 1 06/09/2016
    Final Design PS&E Received - Resub 2 07/25/2016
    Final Design PS&E Received - Resub 3 08/18/2016