Project Description:
DARTMOUTH- CORRIDOR IMPROVEMENTS ON ROUTE 6, FROM FAUNCE CORNER ROAD TO HATHAWAY ROAD
Route 6 (State Road) between Faunce Corner Mall Road and Hathaway Road (the third phase of the Faunce Corner Road corridor improvements) will be upgraded to improve congestion and safety along the project corridor. The project will incorporate a new traffic signal at Route 6 and Hathaway Road as well as introduce a coordinated signal system between Faunce Corner Mall Road and Hathaway Road. The project will reconfigure the offset intersection between Route 6, Tucker Road, and Champion Terrance. This reconfiguration will provide additional storage length on Route 6 approaching Tucker Road and restrict Champion Terrace to a right in right out movement. The project will incorporate longer turn lanes to improve capacity along the corridor. Sidewalks will be upgraded to 8’ in width to coincide with MassDOT’s Complete Streets to provide bicycle and pedestrian accommodations and promote the MassDOT Healthier initiative. Utility poles will be relocated and drainage improvements will be incorporated to the maximum extent practicable.
Location:
  • Town of Dartmouth
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Summer 2026
    Project Manager: Thomas H Currier
    Estimated Total Contract Cost: $11,687,022.05
    Estimated Total Federal Participating Construction Cost: $10,995,722.94
    Funding Provision: This project is planned to be funded through the 2025 Transportation Improvement Program for the Southeastern Massachusetts Metropolitan Planning Organization.
    District: District 5
    Current Status: 75% Package Received (as of 10/16/2023 )

    Contracts (1) Progress
    # 77887 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2025
    Responsible MPO: Southeastern Massachusetts Metropolitan Planning Organization
    Location: Municipality
    Cities: DARTMOUTH
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • a) Construction; b) Total Cost = $10,357,696; Statewide STBG $4,250,000, STBG $3,829,003 and CMAQ $2,693,001 d) EC Score 70 of 100; h) Project Proponent - Dartmouth/MassDOT; i) Status Pre 25%
  • Category FA - Congestion Mitigation/Air Quality (CMAQ)
    Federal Cost: $2,154,400.80
    State Cost: $538,600.20
    Total Cost: $2,693,001.00

    Planned Federal FY: 2025
    Responsible MPO: Southeastern Massachusetts Metropolitan Planning Organization
    Location: Municipality
    Cities: DARTMOUTH
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • a) Construction; b) Total Cost = $10,357,696; Statewide STBG $4,250,000, STBG $3,829,003 and CMAQ $2,693,001 d) EC Score 70 of 100; h) Project Proponent - Dartmouth/MassDOT; i) Status Pre 25%
  • Category FA - Surface Trans. Block Grant (STBG)
    Federal Cost: $3,063,202.40
    State Cost: $765,800.60
    Total Cost: $3,829,003.00

    Planned Federal FY: 2025
    Responsible MPO: Southeastern Massachusetts Metropolitan Planning Organization
    Location: Municipality
    Cities: DARTMOUTH
    Category: Advertised Projects Constr.
    Budget Section: 2B
    Advance Construct: No
    Air Quality Exempt: No

  • a) Construction; b) Total Cost = $10,357,696; Statewide STBG $4,250,000, STBG $3,829,003 and CMAQ $2,693,001 d) EC Score 70 of 100; h) Project Proponent - Dartmouth/MassDOT; i) Status Pre 25%
  • Category FA - Surface Trans. Block Grant (STBG)
    Federal Cost: $3,400,000.00
    State Cost: $850,000.00
    Total Cost: $4,250,000.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/21/2014
    Project Initiation Form PIF Entered 02/21/2014
    Project Initiation Form PRC Submitted 02/21/2014
    Project Review Committee PRC Approved 04/07/2014
    Project Management
    25% Design 25% Package Received 04/28/2014
    25% Design 25% Package Comments to DE 07/31/2015
    25% Design 25% Package Comments to DE 09/24/2021
    25% Design 25% Package Received - Resub 1 02/11/2019
    25% Design 25% Package Received - Resub 2 08/20/2021
    25% Design Design Public Hearing 03/29/2023
    75% Design 75% Package Received 10/16/2023