Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
BOSTON- FIRE STANDPIPE SUPPORT REPAIRS ON I-90 & ASSOCIATED RAMPS (CRC 31)
Scope includes the investigation, design, and construction of the repair of fire standpipe supports that have failed in Ramp L, I-90 EB, I90 WB, Ramp D, and HOV EB. These deficiencies are located near the I-90 portal in South Boston.
Location:
  • City of Boston
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Winter 2022/2023
    Project Manager: Steven E McLaughlin
    Estimated Total Contract Cost: $1,265,000.00
    Estimated Total Federal Participating Construction Cost: N/A
    District: District 6
    Current Status: This project is in the preliminary design phase.

    Contracts (1) Progress
    # 77866 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/26/2014
    Project Initiation Form PIF Entered 02/26/2014
    Project Initiation Form PRC Submitted 03/17/2014
    Project Review Committee PRC Approved 03/25/2014
    Project Management