Project Description:
LOWELL- ROURKE BRIDGE REPLACEMENT, L-15-088, WITH NEW BRIDGE, L-15-114, WOOD STREET EXTENSION OVER MERRIMACK RIVER AND MBTA/CSX RAILROAD
The proposed project replaces the temporary Rourke Bridge structure with a permanent bridge. The bridge will have increased capacity providing two travel lanes in each direction, plus shoulders (able to accommodate bicycles) and sidewalks on either side of the bridge. Intersections at either end of the bridge will be reconstructed, as well as portions of Wood Street, Pawtucket Boulevard, and Old Ferry Road. The improvements include geometric changes, new signal systems and roadway widening.
Location:
  • City of Lowell
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Winter 2024/2025
    Project Manager: Steven E McLaughlin
    Estimated Total Contract Cost: $229,738,040.40
    Estimated Total Federal Participating Construction Cost: $237,805,039.19
    District: District 4
    Current Status: This project has been advertised for construction bids. (as of 09/14/2024 )

    Contracts (1) Progress
    # 77867 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/07/2014
    Project Initiation Form PIF Entered 03/10/2014
    Project Initiation Form PRC Submitted 03/10/2014
    Project Review Committee PRC Approved 08/01/2014
    Project Status Advertised 09/14/2024
    Project Management
    25% Design 25% Package Received 06/01/2023
    25% Design 25% Package Comments to DE 07/11/2023
    25% Design 25% Package Received - Resub 1 12/23/2023
    25% Design Design Public Hearing 12/06/2023
    Final Design PS&E Received 08/14/2024
    Final Design PS&E to FAPRO 09/03/2024
    Final Design PS&E Received - Resub 1 09/18/2024
    Consultant Contract Process NTP Issued 10/09/2019