Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
BOSTON- MULTI-USE PATH CONSTRUCTION ON NEW FENWAY (PHASE I)
The Phase 1 multi-use path project will construct a new 12 foot wide paved bike/pedestrian pathway from Maitland/Overland Street to Miner Street in Boston for a total length of approximately 564 feet. This phase combined with other phases (2 & 3) will work toward improving access to the Fenway MBTA Greenline Station and the Yawkey Commuter Rail station and also work toward providing a non-motorized transportation link to key job centers and new mixed-use developments planned for the Fenway area. (Phase 2 from Miner Street to the Green Line Station will be completed by Landmark Center. Phase 3 from Greenline Station to the Muddy River Park will be constructed under a separate contract and file number).
Location:
  • City of Boston
  • Construction Begins: Autumn 2021
    Resident Engineer: Ahmad Ilyas
    Construction Bid Price: $921,953.00
    District: District 6

    Contracts (1) Progress
    # 116110 -- Construction Contract
    Construction of a Multi-Use Path (Fenway Path) from Miner Street to Maitland Street (Phase 1) Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 11/02/2021
    Contract Information
    Project Designer: Municipality
    Funding Source: CONGESTION MIT. AIR QUAL.
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/07/2014
    Project Initiation Form PIF Entered 03/07/2014
    Project Initiation Form PRC Submitted 03/11/2014
    Project Review Committee PRC Approved 04/07/2014
    Project Status Advertised 08/21/2021
    Project Management
    100% Design 100% Package Received 05/20/2020
    100% Design 100% Package Comments to DE 06/29/2020
    25% Design 25% Package Received 04/07/2014
    25% Design 25% Package Comments to DE 02/24/2015
    25% Design 25% Package Approved 09/19/2017
    25% Design Design Public Hearing 11/29/2017
    75% Design 75% Package Received 03/09/2018
    75% Design 75% Package Received 03/21/2019
    75% Design 75% Package Comments to DE 08/30/2019
    75% Design 75% Package Rejected 03/12/2018
    Final Design PS&E Received 10/26/2020
    Final Design PS&E Received - Resub 1 05/14/2021
    Final Design PS&E Received - Resub 2 08/04/2021