BEVERLY- RESURFACING AND RELATED WORK ON ROUTE 128
The work included in this contract will be milling and paving mainline and ramps on Route 128. Guardrail improvements, drainage structure rebuilding and resetting, and line striping are also included.
Location:
  • City of Beverly
  • Resident Engineer: Marc Schifano
    Construction Contract Value: $6,941,624.63
    Construction Bid Price: $6,042,687.15
    Initial Construction Estimate: $5,016,000.00
    District: District 4

    Contracts (1) Progress
    # 85975 -- Construction Contract
    Resurfacing and Related Work (Including 3 Bridges) along a Section of Route 128 (Yankee Division Highway). Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 07/14/2015
    Contract Information
    Project Designer: In-House Boston
    Funding Source: NATIONAL HIGHWAY SYSTEM
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/12/2014
    Project Initiation Form PIF Entered 05/21/2014
    Project Initiation Form PRC Submitted 05/21/2014
    Project Review Committee PRC Approved 06/12/2014
    Project Status Advertised 12/06/2014
    Project Management
    100% Design 100% Package Received 11/07/2014
    25% Design 25% Package Received 08/18/2014
    75% Design 75% Package Received 08/18/2014
    75% Design 75% Package Comments to DE 08/19/2014
    75% Design 75% Package Comments to DE 08/25/2014
    75% Design 75% Package Comments to DE 10/07/2014
    Final Design PS&E Received 12/03/2014
    Final Design PS&E to FAPRO 12/03/2014