Project Description:
SOMERVILLE- IMPROVEMENTS AT HEALEY SCHOOL (SRTS)
The project includes pedestrian safety improvements and signal upgrades at the intersection of Mystic Avenue and Temple Street. New signal equipment and countdown pedestrian indications will be installed at each crosswalk. The channelized right-turn lane from Mystic Avenue onto Temple Street will be removed and a bump-out will be constructed on the northwest corner of the intersection to improve pedestrian safety. Construction of this bump-out will require drainage modifications. A section of the scored concrete median on Mystic Avenue will also be reconstructed. Other intersection improvements include an asphalt pavement overlay and reprogramming pedestrian phases at necessary to meet MUTCD standards. These improvements will include the installation of ADA-compliant wheelchair ramps and MUTCD compliant pavement markings.
Location:
  • City of Somerville
  • Construction Begins: Spring 2016
    Resident Engineer: Brian McKenney
    Construction Bid Price: $944,132.02
    District: District 4

    Contracts (2) Progress
    # 64315 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 90725 -- Construction Contract
    Sidewalk Reconstruction and Related Work at the Intersection of Route 38 (Mystic Avenue) and Temple Road/Street (Safe Routes to School – Healy School). Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 04/20/2016
    Contract Information
    Project Designer: Consultant
    Funding Source: TAP
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/14/2014
    Project Initiation Form PIF Entered 03/17/2014
    Project Initiation Form PRC Submitted 03/17/2014
    Project Review Committee PRC Approved 04/07/2014
    Project Status Advertised 09/19/2015
    Project Management
    100% Design 100% Package Received 04/06/2015
    100% Design 100% Package Comments to DE 07/06/2015
    25% Design 25% Package Received 08/28/2014
    25% Design 25% Package Comments to DE 02/02/2015
    75% Design 75% Package Received 08/28/2014
    75% Design 75% Package Comments to DE 02/02/2015
    Final Design PS&E Received 08/31/2015
    Final Design PS&E to FAPRO 09/15/2015