Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
DISTRICT 5- DRAWBRIDGE OPERATION, REPAIR & SYSTEMATIC PRESERVATION AT VARIOUS LOCATIONS
This contract is for Scheduled & Emergency Drawbridge Repairs for our movable bridge inventory in District 5.
Location:
Resident Engineer: Louis daPonte
Construction Bid Price: $3,506,522.00
District: District 5

Contracts (1) Progress
# 87529 -- Construction Contract
Scheduled and Emergency Drawbridge Operation and Repairs at Various Locations (Including Martha’s Vineyard) Completed

Bridges

Contract Dates
Notice to Proceed: 06/02/2015
Contract Information
Project Designer: In-House Boston
Funding Source: Non Federal Aid
See the Milestone Details tab for additional Project information
Property Impacts - Right of Way
no comments
Environmental Impacts
no comments
Project Design
no comments
Project Funding
no comments
Public Involvement
no comments
Construction
no comments
Accelerated Bridge Program
no comments
No TIP Data Available For This Project
Project Task Information
Project Status
Project Need Form PNF Entered 03/17/2014
Project Initiation Form PIF Entered 03/17/2014
Project Initiation Form PRC Submitted 03/17/2014
Project Review Committee PRC Approved 03/25/2014
Project Status Advertised 03/21/2015
Project Management
100% Design 100% Package Received 03/05/2015
Final Design PS&E Received 03/10/2015
Final Design PS&E Received 04/09/2015
Final Design PS&E to FAPRO 03/11/2015
Final Design PS&E to FAPRO 04/14/2015