DISTRICT 5- SYSTEMATIC BRIDGE PRESERVATION ALONG THE I-495 CORRIDOR
This contract is to clean various components of the district's bridges to prevent the accumulation of deleterious materials such as salt, pigeon debris from deteriorating the various components.
Location:
Construction Begins: Summer 2018
Resident Engineer: Eric Borman
Construction Bid Price: $1,341,746.25
District: District 5

Contracts (1) Progress
# 102727 -- Construction Contract
Bridge Structure Repairs and Related Work (Including Painting) along Sections of Interstate 495. Completed

Bridges

Contract Dates
Notice to Proceed: 07/13/2018
Contract Information
Project Designer: In-House Boston
Funding Source: NATIONAL HIGHWAY PERFORMANCE PROGRAM ON SYSTEM BRIDGE PROGRAM
See the Milestone Details tab for additional Project information
Initiation
no comments
Scoping
no comments
Property Impacts - Right of Way
no comments
Environmental Impacts
no comments
Project Design
no comments
Project Funding
no comments
Public Involvement
no comments
Construction
no comments
Accelerated Bridge Program
no comments
No TIP Data Available For This Project
Project Task Information
Project Status
Project Need Form PNF Entered 03/17/2014
Project Initiation Form PIF Entered 03/17/2014
Project Initiation Form PRC Submitted 03/17/2014
Project Review Committee PRC Approved 03/25/2014
Project Status Advertised 11/11/2017
Project Management
100% Design 100% Package Received 07/10/2017
Final Design PS&E Received 07/14/2017
Final Design PS&E to FAPRO 10/26/2017