Project Description:
DEDHAM- PEDESTRIAN IMPROVEMENTS ALONG BUSSEY STREET, INCLUDING SUPERSTRUCTURE REPLACEMENT, D-05-010, BUSSEY STREET OVER MOTHER BROOK
Improvements along the Bussey Street corridor will inlcude resetting and setting the curb and reconstructing ADA compliant sidewalks and ramps on both sides of the roadway. Some area of pavement reconstruction may be necessary to obtain the necessary curb reveal. Minor geometric improvements are expected at the intersection with Colburn Street and Clisby Avenue to make them more pedestrian friendly, current conditions include expansive pavement width. Shared bicycle accomodations are planned
Location:
  • Town of Dedham
  • Construction Begins: Spring 2023
    Resident Engineer: Jeovanny Rodriguez
    Construction Bid Price: $7,149,395.00
    District: District 6

    Contracts (2) Progress
    # 115745 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final
    # 121399 -- Construction Contract
    Roadway Reconstruction and Related Work including Superstructure Replacement Br. No. D-05-010 (Pre-Stressed Concrete Deck Beams) along a Section of Bussey Street over Mother B 74% Complete

    Bridges

    Contract Dates
    Notice to Proceed: 05/17/2023
    Contract Information
    Project Designer: Municipality
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/18/2014
    Project Initiation Form PIF Entered 03/18/2014
    Project Initiation Form PRC Submitted 03/19/2014
    Project Review Committee PRC Approved 04/07/2014
    Project Status Advertised 02/11/2023
    Project Management
    100% Design 100% Package Received 06/21/2022
    100% Design 100% Package Comments to DE 08/17/2022
    25% Design 25% Package Received 03/27/2015
    25% Design 25% Package Comments to DE 07/31/2015
    25% Design 25% Package Approved 09/17/2020
    25% Design Design Public Hearing 12/09/2020
    25% Design 25% Plans Complete 08/13/2020
    75% Design 75% Package Received 01/24/2022
    75% Design 75% Package Comments to DE 04/25/2022
    Final Design PS&E Received 11/14/2022
    Final Design PS&E to FAPRO 01/30/2023