Project Description:
PITTSFIELD- TRAFFIC SIGNAL AND INTERSECTION IMPROVEMENTS AT CENTER STREET AND WEST HOUSATONIC STREET (ROUTE 20)
This 4-leg signalized intersection has been identified by the Berkshire Regional Planning Commission (BRPC) and MassDOT as being eligible for improvements under the Highway Safety Improvement Program (HSIP). In addition to safety, there are opportunities to improve bicycle and pedestrian accommodation, intersection geometry, capacity, and regional traffic management.
Location:
  • City of Pittsfield
  • Construction Begins: Winter 2016/2017
    Resident Engineer: Darin Aitken
    Construction Bid Price: $2,372,226.15
    District: District 1

    Contracts (1) Progress
    # 97594 -- Construction Contract
    Intersection Improvements and Related Work (Including Signals) Route 20 (West Housatonic Street) at Center and Elizabeth Streets. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 01/27/2017
    Contract Information
    Project Designer: Municipality
    Funding Source: CONGESTION MIT. AIR QUAL.
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/19/2014
    Project Initiation Form PIF Entered 03/25/2014
    Project Initiation Form PRC Submitted 03/25/2014
    Project Review Committee PRC Approved 04/07/2014
    Project Status Advertised 08/27/2016
    Project Management
    100% Design 100% Package Received 05/05/2016
    100% Design 100% Package Comments to DE 06/06/2016
    25% Design 25% Package Received 09/28/2015
    25% Design 25% Package Comments to DE 11/09/2015
    25% Design Design Public Hearing 12/16/2015
    75% Design 75% Package Received 05/05/2016
    75% Design 75% Package Comments to DE 06/06/2016
    Final Design PS&E Received 07/13/2016
    Final Design PS&E to Peer Reviewer 07/15/2016
    Final Design Peer Review Comments to DE 07/29/2016
    Final Design PS&E to FAPRO 08/22/2016
    Final Design PS&E Received - Resub 1 09/16/2016