GRAFTON- RECLAMATION ON ROUTE 122A (MAIN STREET), FROM PROVIDENCE ROAD TO SUTTON T.L.
The project involves reclamation of Route 122A, from Providence Road to the Sutton Town Line, a disance of 2.05 miles. Additional work includes sidewalk reconstruction, new sidewalk construction,minor geometric intersection improvements, and related work.
Location:
  • Town of Grafton
  • Construction Begins: Summer 2021
    Resident Engineer: Michael Chauvin
    Construction Bid Price: $7,189,512.00
    District: District 3

    Contracts (1) Progress
    # 114313 -- Construction Contract
    Resurfacing and Related Work on a Section of Route 122A (Main Street) Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 07/06/2021
    Contract Information
    Project Designer: Municipality
    Funding Source: FA - Surface Trans. Block Grant (STBG)
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/19/2014
    Project Initiation Form PIF Entered 03/19/2014
    Project Initiation Form PRC Submitted 03/17/2014
    Project Review Committee PRC Approved 04/07/2014
    Project Status Advertised 04/03/2021
    Project Management
    100% Design 100% Package Received 05/15/2020
    25% Design 25% Package Received 02/14/2017
    25% Design 25% Package Comments to DE 08/21/2017
    25% Design Design Public Hearing 02/27/2019
    75% Design 75% Package Received 10/28/2019
    75% Design 75% Package Comments to DE 01/27/2020
    Final Design PS&E Received 10/14/2020
    Final Design PS&E Received - Resub 1 02/16/2021
    Final Design PS&E Received - Resub 2 03/05/2021