Project Description:
HOLDEN- BRIDGE MAINTENANCE OF H-18-028 & 029, I-190 OVER RIVER STREET & QUINAPOXET RIVER
The scope of this project will include milling the existing bituminous wearing surface; patching and waterproof the deck and repaving. The project will include other miscellaneous work such as applying protective sealent to the concrete parapets, replacing drains..etc.
Location:
  • Town of Holden
  • Construction Begins: Summer 2019
    Resident Engineer: Wayne Richard
    Construction Bid Price: $3,385,644.00
    District: District 3

    Contracts (1) Progress
    # 106754 -- Construction Contract
    Bridge Repairs and Related Work Br. Nos. H-18-028 & H-18-029 (Steel) Interstate 190 over River Street and the Quinapoxet River Completed

    Bridges

    Contract Dates
    Notice to Proceed: 06/26/2019
    Contract Information
    Project Designer: In-House Boston
    Funding Source: NATIONAL HIGHWAY PERFORMANCE PROGRAM ON SYSTEM BRIDGE PROGRAM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/21/2014
    Project Initiation Form PIF Entered 03/21/2014
    Project Initiation Form PRC Submitted 03/21/2014
    Project Review Committee PRC Approved 04/10/2014
    Project Status Advertised 12/29/2018
    Project Management
    Final Design PS&E Received 11/19/2018
    Final Design PS&E to FAPRO 12/17/2018