| Project Description: |
FRAMINGHAM- DECK, JOINT & SUBSTRUCTURE REPAIRS ON F-07-018, MOUNT WAYTE AVENUE OVER MBTA/CSX
This project will address to the substructure deterioration at this location caused by leaky and will include repair to deck, joints, sidewalks and railing
|
| Location: |
|
| Resident Engineer: | Nicholas Heath![]() |
| Construction Contract Value: | $1,978,118.40 |
| Construction Bid Price: | $1,214,403.00 |
| Initial Construction Estimate: | $876,000.00 |
| District: | District 3 |
|
Bridges
|
||||||||
|
||||||||||
|
|
|
||||||||||||||||||||||||||||||||