Project Description:
NEWTON- WELLESLEY- WESTON- BRIDGE MAINTENANCE OF N-12-063, N-12-054, N-12-055 & N-12-056 ON I-95/ROUTE 128
This project involves the systematic bridge maintenance of 4 bridges. N-12-063, N-12-054, N-12-055 and N-12-056
Location:
  • City of Newton
  • Town of Wellesley
  • Town of Weston
  • Construction Begins: Autumn 2018
    Resident Engineer: Christopher Ray
    Construction Bid Price: $969,875.00
    District: District 6

    Contracts (1) Progress
    # 102731 -- Construction Contract
    Substructure, Deck Repairs and Related Work (Including Painting) on 4 Bridges along Interstate 95. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 10/04/2018
    Contract Information
    Project Designer: In-House Boston
    Funding Source: NATIONAL HIGHWAY PERFORMANCE PROGRAM ON SYSTEM BRIDGE PROGRAM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/27/2014
    Project Initiation Form PIF Entered 03/27/2014
    Project Initiation Form PRC Submitted 03/27/2014
    Project Review Committee PRC Approved 04/07/2014
    Project Status Advertised 11/11/2017
    Project Management
    Final Design PS&E Received 07/31/2017
    Final Design PS&E to FAPRO 10/19/2017