AUBURN TO WORCESTER- GUIDE & TRAFFIC SIGN REPLACEMENT ON A SECTION OF INTERSTATE 290
This project will consist of the replacement of traffic signs and support structures on I-290 between I-90 in Auburn and I-190 in Worcester and applicable signs on intersecting secondary roadways. This project will improve safety for drivers by incorporating the latest retro-reflective materials into the new signs.
Location:
  • Town of Auburn
  • Town of Shrewsbury
  • Construction Begins: Autumn 2018
    Resident Engineer: Klodian Polisi
    Construction Bid Price: $4,251,734.60
    District: District 3

    Contracts (1) Progress
    # 102812 -- Construction Contract
    Fabrication and Installation of Overhead and Ground Mounted Guide and Traffic Signs along Sections of Interstates 190, 290 and 395. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 10/03/2018
    Contract Information
    Project Designer: Consultant
    Funding Source: Highway Safety Improvement Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/27/2014
    Project Initiation Form PIF Entered 09/24/2014
    Project Initiation Form PRC Submitted 09/24/2014
    Project Review Committee PRC Approved 11/06/2014
    Project Status Advertised 11/25/2017
    Project Management
    100% Design 100% Package Received 06/05/2017
    100% Design 100% Package Comments to DE 07/10/2017
    100% Design 100% Plans Approved 07/07/2017
    25% Design 25% Package Received 10/12/2016
    25% Design 25% Package Comments to DE 01/27/2017
    25% Design 25% Package Approved 01/26/2017
    Final Design PS&E Received 08/04/2017
    Final Design PS&E to FAPRO 11/09/2017