Project Description:
BOLTON TO LOWELL- GUIDE & TRAFFIC SIGN REPLACEMENT ON A SECTION OF INTERSTATE 495
This project consists of replacing the traffic signs and supports on I-495 between Route 111 in Bolton and US Route 3/Lowell Connector in Lowell, inclduing applicable signing on intersecting secondary roadways. This project will improve safety for drivers by incorproating the latest retro-reflective materials into the new signs.
Location:
Construction Begins: Spring 2019
Resident Engineer: Jeffrey Gorczynski
Construction Bid Price: $3,781,054.80
District: District 3

Contracts (1) Progress
# 105834 -- Construction Contract
Fabrication, Installation and Removal of Overhead and Ground Mounted Guide and Traffic Signs along a Section Interstate 495 Completed

Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 03/28/2019
    Contract Information
    Project Designer: Consultant
    Funding Source: Highway Safety Improvement Program
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/27/2014
    Project Initiation Form PIF Entered 09/24/2014
    Project Initiation Form PRC Submitted 09/24/2014
    Project Review Committee PRC Approved 11/06/2014
    Project Status Advertised 09/08/2018
    Project Management
    100% Design 100% Package Received 06/21/2018
    100% Design 100% Package Comments to DE 07/16/2018
    100% Design 100% Plans Approved 07/10/2018
    25% Design 25% Package Received 03/26/2018
    25% Design 25% Package Comments to DE 03/28/2018
    75% Design 75% Package Received 06/21/2018
    Final Design PS&E Received 08/13/2018
    Final Design PS&E to FAPRO 08/24/2018
    Consultant Contract Process NTP Issued 02/06/2018
    Consultant Contract Process Workhours Approved 02/06/2018