Project Description:
MILTON- IMPROVEMENTS AT GLOVER ELEMENTARY SCHOOL IN THE VICINITY OF CANTON AVENUE, BROOKS ROAD AND VOSES LANE (SRTS)
Planned improvements include the construction of a sidewalk with granite curbing and tree wells within a wider paved apron along the westerly side of the Turner Pond parking lot between Brook Road and the pedestrian bridge to the school to eliminate the need for the existing portable concrete barriers and provide standard separation between pedestrians and vehicles accessing the parking lot. The sidewalk along the west side of Canton Avenue from Elm Lawn Street to Brook Road will be reconstructed to a consistent 5’ width with vertical granite curb. The dense trees on the northeast corner of the intersection will be removed to improve sightlines. Voses Lane between Canton Avenue and Brook Road will be converted to a one-way north-westbound flow. Sidewalks will also be constructed along the southerly side of Voses Lane and on both sides of Brook Road. The existing crosswalk on Brook Road just east of the Turner Pond parking area will be removed and relocated to a mid-block location between Voses Lane and Canton Avenue with new pedestrian flasher assemblies. An ornamental fence in the median on Brook Road between the raised crosswalk and Canton Avenue will be installed to channelize pedestrians toward the relocated crosswalk. These improvements will include installation of ADA-compliant wheelchair ramp, installation of MUTCDcompliant signs and pavement markings, and minor drainage improvements.
Location:
  • Town of Milton
  • Construction Begins: Winter 2015/2016
    Resident Engineer: Michael Leonard
    Construction Bid Price: $865,955.00
    District: District 6

    Contracts (3) Progress
    # 64315 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 85766 -- Design -- Highway
    Work will consist of providing school assessments and preliminary and final engineering design and construction phase services to the Highway Engineering Division for the 2014 Final
    # 90578 -- Construction Contract
    Sidewalk Reconstruction and Related Work on Sections of Brook Road, Canton Avenue, and adjacent Streets (Safe Routes to School – Glover Elementary School). Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 03/04/2016
    Contract Information
    Project Designer: Consultant
    Funding Source: TAP
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/28/2014
    Project Initiation Form PIF Entered 03/28/2014
    Project Initiation Form PRC Submitted 03/31/2014
    Project Review Committee PRC Approved 04/07/2014
    Project Status Advertised 09/12/2015
    Project Management
    100% Design 100% Package Received 04/10/2015
    100% Design 100% Package Comments to DE 06/25/2015
    25% Design 25% Package Received 05/02/2014
    25% Design 25% Package Comments to DE 09/17/2014
    25% Design Design Public Hearing 10/23/2014
    75% Design 75% Package Received 05/02/2014
    Final Design PS&E Received 07/13/2015
    Final Design PS&E to FAPRO 09/07/2015