Project Description:
LEICESTER- BRIDGE REPLACEMENT, L-06-017, RAWSON STREET OVER THE CEDAR MEADOW POND INLET
This project is for replacing the existing Bridge that carries Rawson Street over the Cedar Meadow Pond iNlet in the Town of Leicester.
Location:
  • Town of Leicester
  • Construction Begins: Autumn 2017
    Resident Engineer: Carmen Ramirez
    Construction Bid Price: $1,198,198.45
    District: District 3

    Contracts (3) Progress
    # 100296 -- Construction Contract
    Bridge Replacement Br. No. L-06-017 (Steel) Rawson Street over the Cedar Meadow Pond Inlet. Completed
    # 69759 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassDOT on an open end basis for various highway and bridge projects. Final
    # 77850 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    Contract Dates
    Notice to Proceed: 12/07/2017
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/28/2014
    Project Initiation Form PIF Entered 03/28/2014
    Project Initiation Form PRC Submitted 03/28/2014
    Project Review Committee PRC Approved 04/07/2014
    Project Status Advertised 04/29/2017
    Project Management
    100% Design 100% Package Received 01/03/2017
    100% Design 100% Package Comments to DE 03/01/2017
    100% Design 100% Plans Approved 03/17/2017
    100% Design 100% Plans Complete 03/17/2017
    25% Design 25% Package Received 06/10/2015
    25% Design 25% Package Received 05/16/2016
    25% Design 25% Package Comments to DE 10/21/2015
    25% Design 25% Package Approved 08/01/2016
    25% Design Design Public Hearing 09/07/2016
    25% Design 25% Plans Complete 09/07/2016
    75% Design 75% Package Received 09/26/2016
    75% Design 75% Package Comments to DE 11/21/2016
    75% Design 75% Plans Approved 12/01/2016
    75% Design 75% Plans Complete 12/01/2016
    Final Design PS&E Received 04/05/2017
    Final Design PS&E to Peer Reviewer 04/24/2017
    Final Design PS&E to FAPRO 04/24/2017
    Consultant Contract Process Workhours Approved 08/11/2014