DISTRICT 5- PAVEMENT REPAIRS AND CRACK SEALING AT VARIOUS LOCATIONS (AREAS A, B & C)
Work on this project consists of pavement repairs and crack sealing at various locations in areas A, B and C of District 5.
Location:
Design Responsibility: In-House Boston
Right of Way Responsibility: MassDOT
Project Manager: Ancarlos M Youssef
Estimated Total Federal Participating Construction Cost: N/A
District: District 5
Current Status: This project has been advertised for construction bids. (as of 07/11/2015 )

Contracts (0) Progress
No contracts associated with this project

Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/28/2014
    Project Initiation Form PIF Entered 03/28/2014
    Project Initiation Form PRC Submitted 03/28/2014
    Project Review Committee PRC Approved 03/31/2014
    Project Status Advertised 01/31/2015
    Project Status Advertised 07/11/2015
    Project Management
    Final Design PS&E Received 12/29/2014
    Final Design PS&E to FAPRO 01/26/2015
    Final Design PS&E to FAPRO 07/08/2015