EAST BRIDGEWATER- RESURFACING AND SIDEWALK CONSTRUCTION ON BEDFORD STREET (ROUTE 18), FROM WHITMAN STREET (ROUTE 106) TO CENTRAL STREET
Work on this project includes the resurfacing of Route 18 and the construction of sidewalks and bicycle lanes along the corridor. Drainage upgrades will be included. Minor intersection improvements at Rte 106 will be incorporated into the project.
Location:
  • Town of East Bridgewater
  • Construction Begins: Spring 2020
    Resident Engineer: Russell Davis
    Construction Bid Price: $7,829,599.00
    District: District 5
    Current Status: Project is complete. Normal work hours are Monday thru Friday, 7:00 AM to 3:30 PM. (as of 04/08/2024)

    Contracts (2) Progress
    # 109470 -- Construction Contract
    Roadway Reconstruction and Related Work (Including Signals) along a Section of Route 18 (Bedford Street) 100% Complete
    # 77852 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 06/09/2020
    Contract Information
    Project Designer: Consultant
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Project is complete. Normal work hours are Monday thru Friday, 7:00 AM to 3:30 PM.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 04/02/2014
    Project Initiation Form PIF Entered 04/02/2014
    Project Initiation Form PRC Submitted 04/02/2014
    Project Review Committee PRC Approved 04/07/2014
    Project Status Advertised 08/24/2019
    Project Management
    100% Design 100% Package Received 01/29/2019
    100% Design 100% Package Comments to DE 03/04/2019
    25% Design 25% Package Received 11/16/2016
    25% Design 25% Package Comments to DE 04/12/2017
    25% Design 25% Package Received - Resub 1 09/11/2017
    25% Design Design Public Hearing 04/04/2018
    75% Design 75% Package Received 06/14/2018
    75% Design 75% Package Comments to DE 08/16/2018
    Final Design PS&E Received 08/05/2019