Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
ASHBURNHAM- INTERSECTION IMPROVEMENTS AT ROUTE 101 & WILLIAMS & COREY HILL ROAD
Intersection improvements and related work, which include construction of a roundabout or installation of a traffic signal, to address safety concerns at the intersection.
Location:
  • Town of Ashburnham
  • Design Responsibility: Consultant
    Right of Way Responsibility: Municipality
    Project Manager: Muazzez G Reardon
    Estimated Total Contract Cost: $1,121,098.16
    Estimated Total Federal Participating Construction Cost: $1,179,554.35
    District: District 3
    Current Status: Design Public Hearing (as of 10/26/2015 )

    Contracts (1) Progress
    # 59943 -- Design -- Traffic Open End
    Work will consist of providing traffic engineering services in connection with the review of project design documents developed through the MEPA process. Final

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 04/03/2014
    Project Initiation Form PIF Entered 04/03/2014
    Project Initiation Form PRC Submitted 04/03/2014
    Project Review Committee PRC Approved 04/07/2014
    Project Management
    25% Design 25% Package Received 07/27/2015
    25% Design 25% Package Comments to DE 09/18/2015
    25% Design Design Public Hearing 10/26/2015
    Consultant Contract Process NTP Issued 07/09/2014