DISTRICT 3- SCHEDULED & EMERGENCY BRIDGE DECK REPAIRS AT VARIOUS LOCATIONS
This contract will address bridge deck deficiencies that would include spalling and delaminated concrete, bridge joint failure, drainage deficiencies, etc.
Location:
Construction Begins: Spring 2017
Resident Engineer: Marghrit Arous
Construction Bid Price: $2,194,529.40
Initial Construction Estimate: $2,257,000.00
District: District 3

Contracts (1) Progress
# 99202 -- Construction Contract
Scheduled and Emergency Bridge Deck Repairs at Various Locations (Re-Advertised Project). 100% Complete

Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 06/07/2017
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 04/12/2014
    Project Initiation Form PIF Entered 04/14/2014
    Project Initiation Form PRC Submitted 04/12/2014
    Project Review Committee PRC Approved 04/14/2014
    Project Status Advertised 10/25/2014
    Project Status Advertised 12/10/2016
    Project Management
    100% Design 100% Package Received 08/13/2014
    Final Design PS&E Received 10/14/2014
    Final Design PS&E Received - Resub 1 10/12/2016