Project Description:
MARION- SHARED USE PATH CONSTRUCTION (PHASE 1), FROM THE MARION-MATTAPOISETT T.L. TO POINT ROAD
Work on this project includes construction of a shared use path in the Town of Marion from the Mattappisett/Mairon Town line to Point Road. This section of path is also part of a larger network immediately connecting Mattapoisett to Wareham, and on a larger scale a part of the Bay State Greenway priority 100 miles and the SouthCoast Bikeway.
Location:
  • Town of Marion
  • Construction Begins: Autumn 2026
    Resident Engineer: Dylan Hipolito
    Construction Bid Price: $5,607,201.60
    Funding Provision: This project is planned to be funded through the 2027 Transportation Improvement Program for the Southeastern Massachusetts Metropolitan Planning Organization.
    District: District 5

    Contracts (2) Progress
    # 115769 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final
    # 136415 -- Construction Contract
    Shared Use Path Construction (Phase 1), from the Marion-Mattapoisett T.L. to Point Road

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 10/21/2026
    Contract Information
    Project Designer: Municipality
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2027
    Responsible MPO: Southeastern Massachusetts Metropolitan Planning Organization
    Location: Municipality
    Cities: MARION
    Category: Advertised Projects Constr.
    Budget Section: 2C
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Congestion Mitigation/Air Quality (CMAQ)
    Federal Cost: $5,168,773.60
    State Cost: $1,292,193.40
    Total Cost: $6,460,967.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 04/23/2014
    Project Initiation Form PIF Entered 12/01/2014
    Project Initiation Form PRC Submitted 01/13/2015
    Project Review Committee PRC Approved 03/20/2015
    Project Status Advertised 08/15/2026
    Project Management
    100% Design 100% Package Received 11/07/2023
    100% Design 100% Package Comments to DE 12/22/2023
    100% Design 100% Package Comments to DE 05/19/2025
    100% Design 100% Package Comments to DE 03/22/2026
    100% Design 100% Package Received - Resub 1 04/15/2025
    100% Design 100% Package Received - Resub 2 02/18/2026
    25% Design 25% Package Received 09/04/2018
    25% Design 25% Package Comments to DE 01/03/2019
    25% Design Design Public Hearing 07/30/2019
    75% Design 75% Package Received 12/29/2020
    75% Design 75% Package Comments to DE 04/25/2021
    75% Design 75% Plans Approved 10/27/2021
    75% Design 75% Plans Complete 10/27/2021
    Final Design PS&E Received 07/07/2026
    Final Design PS&E to FAPRO 11/02/2026
    Final Design PS&E Received - Resub 1 07/27/2026
    Consultant Contract Process NTP Issued 05/09/2016