Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
LAWRENCE- NORTH ANDOVER- INTERSTATE MAINTENANCE & RELATED WORK ON I-495
Project consists of highway and bridge resurfacing, safety and environmental improvements.
Location:
  • City of Lawrence
  • Town of North Andover
  • Resident Engineer: James Slavit
    Construction Contract Value: $7,866,822.53
    Construction Bid Price: $6,851,977.30
    Initial Construction Estimate: $6,491,000.00
    District: District 4

    Contracts (1) Progress
    # 85976 -- Construction Contract
    Resurfacing and Related Work (Including 7 Bridges) along a Section of Interstate 495. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 05/27/2015
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Interstate Maintenance
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/15/2014
    Project Initiation Form PIF Entered 05/15/2014
    Project Initiation Form PRC Submitted 05/15/2014
    Project Review Committee PRC Approved 06/12/2014
    Project Status Advertised 12/06/2014
    Project Management
    100% Design 100% Package Received 11/07/2014
    100% Design 100% Package Comments to DE 11/12/2014
    100% Design 100% Package Comments to DE 11/21/2014
    100% Design 100% Package Comments to DE 11/24/2014
    75% Design 75% Package Received 09/04/2014
    75% Design 75% Package Comments to DE 10/06/2014
    75% Design 75% Package Comments to DE 10/06/2014
    75% Design 75% Package Comments to DE 10/07/2014
    Final Design PS&E Received 11/07/2014
    Final Design PS&E Received 03/10/2015
    Final Design PS&E to FAPRO 12/03/2014