Project Description:
ANDOVER- BEDFORD- BILLERICA- STORMWATER IMPROVEMENTS ALONG I-93, ROUTE 3 AND ROUTE 3A
This project will provide for upgrading stormwater infrastructure for impaired water bodies at various locations.
Location:
  • Town of Andover
  • Town of Bedford
  • Town of Billerica
  • Construction Begins: Winter 2017/2018
    Resident Engineer: Stephen Doherty
    Construction Bid Price: $1,730,756.85
    District: District 4

    Contracts (1) Progress
    # 100371 -- Construction Contract
    Drainage Improvements and Related Work along Sections of Interstate 93 and Routes 3 and 3A. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 12/21/2017
    Contract Information
    Project Designer: Consultant
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/27/2014
    Project Initiation Form PIF Entered 05/27/2014
    Project Initiation Form PRC Submitted 05/27/2014
    Project Review Committee PRC Approved 08/01/2014
    Project Status Advertised 05/06/2017
    Project Management
    100% Design 100% Package Received 01/13/2017
    100% Design 100% Package Comments to DE 02/21/2017
    25% Design 25% Package Received 06/10/2016
    25% Design 25% Package Comments to DE 09/07/2016
    Final Design PS&E Received 03/31/2017
    Final Design PS&E to Peer Reviewer 04/04/2017
    Final Design Peer Review Comments to DE 04/11/2017
    Final Design PS&E to FAPRO 04/24/2017