Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
AYER- NATICK- LANCASTER- LEOMINSTER- WORCESTER- STORMWATER IMPROVEMENTS ALONG ROUTE 2, ROUTE 9, ROUTE 12, ROUTE 2A, ROUTE 110, ROUTE 111 AND I-290
This project will provide for upgrading stormwater infrastructure for impaired water bodies at various locations in the District.
Location:
  • Town of Ayer
  • Town of Lancaster
  • City of Leominster
  • Town of Natick
  • City of Worcester
  • Construction Begins: Spring 2019
    Resident Engineer: Christopher Lee
    Construction Bid Price: $980,030.00
    District: District 3

    Contracts (2) Progress
    # 105764 -- Construction Contract
    Stormwater Drainage Improvements and Related Work at Various Locations Completed
    # 86790 -- Design -- Services
    AutoCAD Base Plan Surveying Services Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 04/03/2019
    Contract Information
    Project Designer: Consultant
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/27/2014
    Project Initiation Form PIF Entered 05/27/2014
    Project Initiation Form PRC Submitted 05/27/2014
    Project Review Committee PRC Approved 08/01/2014
    Project Status Advertised 09/01/2018
    Project Management
    100% Design 100% Package Received 06/12/2018
    100% Design 100% Package Comments to DE 07/13/2018
    75% Design 75% Package Received 01/02/2018
    75% Design 75% Package Comments to DE 02/09/2018
    75% Design 75% Plans Approved 02/09/2018
    Final Design PS&E Received 08/09/2018
    Final Design PS&E to FAPRO 08/20/2018