Project Description:
EVERETT- IMPROVEMENTS AT MADELAINE ENGLISH (SRTS)
This project includes the construction of 8-10 foot wide ramps with retaining walls from the school to the Northern Strand Community Trail, reconstruction of existing sidewalk along the southern perimeter of the school property, reconstruction of the Tremont Street / Bell Rock Street intersection to improve traffic flow, and the installation of five foot wide sidewalk connections with vertical granite curb along Wyliss Avenue, Prescott Street, and Waters Avenue.
Location:
  • City of Everett
  • Construction Begins: Spring 2017
    Resident Engineer: Brian McKenney
    Construction Bid Price: $711,000.00
    District: District 4

    Contracts (2) Progress
    # 85766 -- Design -- Highway
    Work will consist of providing school assessments and preliminary and final engineering design and construction phase services to the Highway Engineering Division for the 2014 Final
    # 97772 -- Construction Contract
    Multi-Use Pathway Construction and Ramp and Sidewalk Connections to the North Strand Community Trail (NSCT) (Safe Routes to School – Madeline English School). Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 03/24/2017
    Contract Information
    Project Designer: Consultant
    Funding Source: TAP
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/29/2014
    Project Initiation Form PIF Entered 10/28/2014
    Project Initiation Form PIF Entered 08/28/2015
    Project Initiation Form PRC Submitted 10/29/2014
    Project Review Committee PRC Tabled 06/25/2015
    Project Review Committee PRC Approved 08/28/2015
    Project Status Advertised 09/10/2016
    Project Management
    100% Design 100% Package Received 08/08/2016
    25% Design 25% Package Received 03/07/2016
    25% Design Design Public Hearing 06/15/2016
    75% Design 75% Package Received 03/07/2016
    75% Design 75% Package Comments to DE 05/24/2016
    Final Design PS&E Received 08/08/2016
    Final Design PS&E to FAPRO 09/05/2016