Project Description:
REVERE- IMPROVEMENTS AT GARFIELD ELEMENTARY & MIDDLE SCHOOL (SRTS)
The project includes the reconstruction of the concrete sidewalk with vertical granite curb along the west side of Waverly Avenue from Centennial Avenue to the intersection of North Shore Road and Dana Street, reconstruction of concrete sidewalk with vertical granite curb along the south side of Dix Street and the reconstruction of concrete sidewalk with vertical granite curb along the east side of Garfield Avenue from Dix Street to the school driveway. High-visibility crosswalks will be constructed and existing signage will be upgraded where applicable. New crosswalk and stop line pavement markings will be applied where faded. ADA-compliant accessible ramps will be constructed for all perpendicular pedestrian crossings and a traffic signal with countdown pedestrian indicators will be installed at the intersection of Waverly Avenue, North Shore Road, and Dana Street. The existing traffic signal at the intersection of North Shore Road and Dix Street will be removed and finally, MUTCD-compliant warning and regulatory signs will be installed throughout the project. All-way stop control will be considered at the intersections of Garfield Avenue with Blake Street and Dix Street.
Location:
  • City of Revere
  • Construction Begins: Spring 2018
    Resident Engineer: George Kavalaris
    Construction Bid Price: $1,012,228.00
    District: District 4

    Contracts (1) Progress
    # 102133 -- Construction Contract
    Roadway Reconstruction and Related Work along Garfield Avenue, North Shore Road and Adjacent Streets (Safe Routes to School-Garfield Elementary and Middle Schools). Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 03/30/2018
    Contract Information
    Project Designer: Consultant
    Funding Source: TAP
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/29/2014
    Project Initiation Form PIF Entered 10/29/2014
    Project Initiation Form PIF Entered 07/10/2015
    Project Initiation Form PRC Submitted 10/29/2014
    Project Review Committee PRC Tabled 11/06/2014
    Project Review Committee PRC Approved 06/25/2015
    Project Status Advertised 09/02/2017
    Project Management
    100% Design 100% Package Received 07/03/2017
    100% Design 100% Package Comments to DE 08/08/2017
    25% Design 25% Package Received 10/21/2016
    25% Design Design Public Hearing 04/26/2017
    75% Design 75% Package Received - Resub 1 03/01/2017
    Final Design PS&E Received 08/18/2017
    Final Design Peer Review Comments to DE 08/14/2017
    Final Design PS&E to FAPRO 08/21/2017